Administrative guide · 2026

Building permit in Senegal (2026)

Competent authority, required documents, timelines and costs: everything you need to obtain your building permit in Senegal, including from the diaspora.

Competent authority

Application filed online via the TéléDAC platform (one-stop shop), processed by the Urban Planning Directorate; DSCOS inspects site compliance.

Timelines

Official processing time of 28 to 40 days via TéléDAC for a complete file.

Costs

Urban planning tax based on floor area and commune, typically a few hundred thousand FCFA for a villa.

The 5 steps of the process

  1. 1

    Secure the land

    Verify the property title with the land registry before spending anything.

  2. 2

    Commission the plans

    From an architect registered with the national board — mandatory above certain floor-area thresholds.

  3. 3

    Assemble the file

    Gather the documents listed below; an incomplete file is the No. 1 cause of delay.

  4. 4

    Submit and track the application

    With the competent authority (or online where available); keep the filing receipt.

  5. 5

    Display the permit and start

    Display the permit on site and comply with the requirements (siting, height, easements).

Required documents

  • Property title, lease or council resolution
  • Architectural plans signed by a registered architect
  • Location plan and site plan
  • Technical study for buildings of 3 storeys and above
  • Project manager's insurance certificate depending on the project

Indicative information subject to change — always confirm the exact list with the local authority or your architect.

Frequently asked questions

Is a building permit mandatory in Senegal?

Yes, any new construction in an urban area requires a permit. Building without one exposes you to fines, a stop-work order or even demolition. Application filed online via the TéléDAC platform (one-stop shop), processed by the Urban Planning Directorate; DSCOS inspects site compliance.

How long does it take to get a permit in Senegal?

Official processing time of 28 to 40 days via TéléDAC for a complete file.

How much does a building permit cost in Senegal?

Urban planning tax based on floor area and commune, typically a few hundred thousand FCFA for a villa.

Can I handle the process from abroad?

Yes, through a power of attorney given to a trusted relative, an architect or a mandated professional. Require a copy of the filing receipt and track progress with proof — DiasporaBuild lets you mandate verified professionals and trace every step.