DiasporaBuild · Market Intel
African Material Prices
A trading-desk view of construction material fluctuations across 15 markets. 12-month charts, insights and real-world prices reported by our experts.
Up
↑ 26
Down
↓ 38
Stable
— 2
Prices tagged “verified”: sourced records under 7 days old (source link available in the details). Prices tagged “estimate”: DiasporaBuild estimate from a USD reference, FX rate and country cost index. 12-month history is simulated. Actual prices vary by city, supplier and negotiation.
NGNigeria
11 tracked materials · USD· refreshed 23/08/2026
| Material | Range | 3 mo. | |
|---|---|---|---|
Cement (50kg bag) Cement · bag | 8,5 – 11 USD | +2.4% | |
Steel (Ton) Steel · ton | 900 – 1 100 USD | -1.8% | |
Sand (m³) Aggregates · m³ | 15 – 25 USD | -11.4% | |
Gravel (m³) Aggregates · m³ | 20 – 35 USD | -12.4% | |
Bricks (1000 units) Masonry · 1000 units | 80 – 120 USD | -10.6% | |
Ready-mixed concrete (m³) Concrete · m³estimate | 99,8 – 152 USD | +1.6% | |
Construction timber (m³) Timber · m³estimate | 252 – 452 USD | -11.4% | |
Mason labour (day) Labour · dayestimate | 7,2 – 17,6 USD | +7.8% | |
Rebar Ø12 (12 m bar) Steel · barestimate | 8,4 – 14,7 USD | -7.9% | |
Roofing sheet (unit) Roofing · sheetestimate | 9,5 – 19,9 USD | -4.7% | |
Floor tiles (m²) Finishing · m²estimate | 7,4 – 21 USD | +11.5% |
What moves prices here
- ■Global stabilization of construction material prices — Les prix des matériaux de construction en 2026 se stabilisent globalement après quatre années de turbulences.
- ■Monitoring of cement price trends and forecasts — Analyse des tendances et prévisions de prix du ciment en 2026, selon les régions (USA, Chine, Europe).
- ■Analysis of infrastructure and demand impacts on cement prices — Analyse des impacts des infrastructures et de la demande sur l'indice des tendances des prix du ciment en 2026.
As a construction economist in Africa, the most notable trend for 2026 is the stabilization of construction material prices, including cement, following a period of turbulence. Ongoing analysis of regional dynamics and the influence of infrastructure on cement demand is underway, contributing to a better understanding of the market. The lack of specific information for Nigeria regarding inflation or diesel prices prevents a more detailed local analysis.
SNSenegal
11 tracked materials · XOF
| Material | Range | 3 mo. | |
|---|---|---|---|
Cement (50kg bag) Cement · bag | 3 500 – 4 000 XOF | +2.2% | |
Steel (Ton) Steel · ton | 600 000 – 650 000 XOF | -1.2% | |
Sand (m³) Aggregates · m³ | 8 000 – 12 000 XOF | -2.4% | |
Gravel (m³) Aggregates · m³ | 15 000 – 20 000 XOF | -1.7% | |
Concrete blocks (unit) Masonry · unit | 350 – 450 XOF | -1.5% | |
Ready-mixed concrete (m³) Concrete · m³estimate | 57 000 – 87 000 XOF | +2.8% | |
Construction timber (m³) Timber · m³estimate | 144 000 – 258 000 XOF | -11.1% | |
Mason labour (day) Labour · dayestimate | 4 900 – 11 900 XOF | -13.1% | |
Rebar Ø12 (12 m bar) Steel · barestimate | 4 800 – 8 400 XOF | -6.3% | |
Roofing sheet (unit) Roofing · sheetestimate | 5 400 – 11 400 XOF | +15.3% | |
Floor tiles (m²) Finishing · m²estimate | 4 200 – 12 000 XOF | +22.0% |
KEKenya
11 tracked materials · KES
| Material | Range | 3 mo. | |
|---|---|---|---|
Cement (50kg bag) Cement · bag | 650 – 800 KES | -1.4% | |
Steel (Ton) Steel · ton | 110 000 – 130 000 KES | +4.8% | |
Sand (m³) Aggregates · m³ | 1 500 – 2 500 KES | +10.6% | |
Gravel (m³) Aggregates · m³ | 2 500 – 4 000 KES | +9.8% | |
Bricks (1000 units) Masonry · 1000 units | 8 000 – 12 000 KES | -7.6% | |
Ready-mixed concrete (m³) Concrete · m³estimate | 12 300 – 18 700 KES | -5.0% | |
Construction timber (m³) Timber · m³estimate | 31 000 – 55 500 KES | -1.1% | |
Mason labour (day) Labour · dayestimate | 1 000 – 2 600 KES | -17.2% | |
Rebar Ø12 (12 m bar) Steel · barestimate | 1 000 – 1 800 KES | +12.5% | |
Roofing sheet (unit) Roofing · sheetestimate | 1 200 – 2 500 KES | +4.7% | |
Floor tiles (m²) Finishing · m²estimate | 900 – 2 600 KES | -13.7% |
CMCameroon
11 tracked materials · XAF
| Material | Range | 3 mo. | |
|---|---|---|---|
Cement (50kg bag) Cement · bag | 4 500 – 5 200 XAF | -1.4% | |
Steel (Ton) Steel · ton | 650 000 – 750 000 XAF | -2.5% | |
Sand (m³) Aggregates · m³ | 10 000 – 15 000 XAF | -5.8% | |
Gravel (m³) Aggregates · m³ | 18 000 – 25 000 XAF | -4.7% | |
Concrete blocks (unit) Masonry · unit | 400 – 550 XAF | +5.5% | |
Ready-mixed concrete (m³) Concrete · m³estimate | 59 800 – 91 400 XAF | -2.2% | |
Construction timber (m³) Timber · m³estimate | 151 200 – 270 900 XAF | +11.1% | |
Mason labour (day) Labour · dayestimate | 4 600 – 11 200 XAF | -16.4% | |
Rebar Ø12 (12 m bar) Steel · barestimate | 5 000 – 8 800 XAF | -7.5% | |
Roofing sheet (unit) Roofing · sheetestimate | 5 700 – 12 000 XAF | -14.1% | |
Floor tiles (m²) Finishing · m²estimate | 4 400 – 12 600 XAF | -16.4% |
CIIvory Coast
11 tracked materials · XOF
| Material | Range | 3 mo. | |
|---|---|---|---|
Cement (50kg bag) Cement · bag | 3 800 – 4 300 XOF | +2.8% | |
Steel (Ton) Steel · ton | 580 000 – 680 000 XOF | +5.7% | |
Sand (m³) Aggregates · m³ | 9 000 – 14 000 XOF | -4.8% | |
Gravel (m³) Aggregates · m³ | 16 000 – 22 000 XOF | -3.5% | |
Concrete blocks (unit) Masonry · unit | 380 – 500 XOF | +1.9% | |
Ready-mixed concrete (m³) Concrete · m³estimate | 57 000 – 87 000 XOF | -0.7% | |
Construction timber (m³) Timber · m³estimate | 144 000 – 258 000 XOF | -8.6% | |
Mason labour (day) Labour · dayestimate | 5 100 – 12 500 XOF | -14.9% | |
Rebar Ø12 (12 m bar) Steel · barestimate | 4 800 – 8 400 XOF | +15.6% | |
Roofing sheet (unit) Roofing · sheetestimate | 5 400 – 11 400 XOF | +1.0% | |
Floor tiles (m²) Finishing · m²estimate | 4 200 – 12 000 XOF | -2.1% |
GHGhana
11 tracked materials · GHS
| Material | Range | 3 mo. | |
|---|---|---|---|
Cement (50kg bag) Cement · bag | 75 – 95 GHS | -2.3% | |
Steel (Ton) Steel · ton | 12 000 – 15 000 GHS | +3.4% | |
Sand (m³) Aggregates · m³ | 150 – 250 GHS | +3.4% | |
Gravel (m³) Aggregates · m³ | 200 – 350 GHS | +3.7% | |
Bricks (1000 units) Masonry · 1000 units | 800 – 1 200 GHS | +10.0% | |
Ready-mixed concrete (m³) Concrete · m³estimate | 1 347 – 2 055 GHS | +11.5% | |
Construction timber (m³) Timber · m³estimate | 3 402 – 6 095 GHS | +14.4% | |
Mason labour (day) Labour · dayestimate | 109 – 267 GHS | -1.2% | |
Rebar Ø12 (12 m bar) Steel · barestimate | 113 – 198 GHS | +10.6% | |
Roofing sheet (unit) Roofing · sheetestimate | 128 – 269 GHS | -13.3% | |
Floor tiles (m²) Finishing · m²estimate | 99,2 – 284 GHS | -21.0% |
Spotted a different price on the ground? Sign in to report it with your invoice or source.
Country not listed?
Type its name: we search public sources and build its sheet. The result is stored and visible to everyone afterwards.
Search reserved for DiasporaBuild accounts (free to create).
Construction material prices in Africa: what the numbers say
This page tracks eleven construction line items across fifteen African markets: cement, steel, rebar, sand, gravel, blocks, ready-mixed concrete, timber, roofing sheets, tiles and labour. Every verified price links back to its public source, with the city and date of the record. The goal is simple: let a diaspora client check whether the quote they received matches the real market, before sending the first transfer.
Cement prices in Africa
Cement is the most closely watched line item on a site: it often accounts for 15 to 25 % of structural works. Gaps between countries mostly come from the presence of a local cement plant, diesel transport cost and duties on imported clinker. A 500 XOF difference per bag shifts the budget of a 200 m² villa by hundreds of thousands of francs.
Steel and rebar prices
Steel tracks global benchmarks and the dollar exchange rate: it is the most volatile material in the table. We track both the ton of steel and the 12 m Ø12 rebar, the unit actually bought on diaspora building sites.
Sand, gravel and ready-mixed concrete
Aggregates are “heavy” materials: their price depends almost entirely on the distance to the quarry. Ready-mixed concrete, still rare outside major cities, becomes competitive as soon as the batching plant is within 30 km of the site and removes on-site mix errors.
Roofing, timber and finishes
Roofing sheets, construction timber and floor tiles are where quality gaps are widest at the same displayed price: sheet thickness, timber species and drying, tile wear rating. We always state the reference unit to avoid misleading comparisons.
Labour: the line item people forget
Labour represents 25 to 40 % of total cost depending on the country and building method. We publish the mason's daily rate, the clearest reference for a diaspora client comparing two quotes.
Frequently asked questions
A 50 kg bag ranges from 4,000 to 7,000 XOF/XAF in West and Central Africa (Cameroon, Senegal, Ivory Coast, Mali), around 8 to 12 USD in Nigeria and Ghana, and roughly 750 to 950 KES in Kenya. Brand, distance to the cement plant and purchase volume all move the price.