Solid slab vs hollow block slab

In short : Two ways to build a floor: the solid slab (full-depth reinforced concrete, heavy but simple) and the hollow block slab (joists + blocks + topping, lighter and cement-saving). Typical choice in Africa: hollow blocks for storeys, solid for short spans and wet areas.
- •Solid slab: depth ≈ span/20 (12-18 cm), mesh or grid rebar
- •Hollow block: 16+4 or 20+5 cm, joists every 60 cm
- •Topping: 4-5 cm + welded mesh mandatory
- •Propping kept minimum 21 days
- ✗Topping without mesh (checkerboard cracking)
- ✗Removing props at 7 days 'because it looks dry'
- ✗Blocks on uncalculated artisanal joists
Frequently asked questions
What is the role of: solid slab vs hollow block slab?
Two ways to build a floor: the solid slab (full-depth reinforced concrete, heavy but simple) and the hollow block slab (joists + blocks + topping, lighter and cement-saving). Typical choice in Africa: hollow blocks for storeys, solid for short spans and wet areas.
What are typical dimensions and rules for solid slab vs hollow block slab?
Solid slab: depth ≈ span/20 (12-18 cm), mesh or grid rebar. Hollow block: 16+4 or 20+5 cm, joists every 60 cm. Topping: 4-5 cm + welded mesh mandatory. Propping kept minimum 21 days.
What mistakes should I avoid with solid slab vs hollow block slab?
Topping without mesh (checkerboard cracking). Removing props at 7 days 'because it looks dry'. Blocks on uncalculated artisanal joists.