Mali
Administrative guide — Building permit
Verified on 29/04/2026
Average delay
150
days
Estimated cost
500,000 – 1,500,000 XOF
Office
National Directorate of Urban Planning and Housing
EDM (Énergie du Mali)
SOMAGEP
Stamped handwritten application addressed to the Mayor/Director of Urban Planning
Land title or proof of ownership (Land Certificate, Lease, etc.)
Site plan and block plan signed by a licensed surveyor
Architectural plans (ground floor, floors, sections, facades) signed and stamped by a licensed architect
Engineering plans (structure, foundations, sanitation) signed and stamped by a licensed engineer
Environmental impact study (for projects of a certain scale)
Copy of the applicant's identification (ID card, passport)
Notarized power of attorney if the application is submitted by a third party