Morocco
Administrative guide — Building permit
Verified on 29/04/2026
Average delay
60
days
Estimated cost
50,000 – 150,000 MAD
Office
Urban Agency / Municipality
ONEE (ONE)
ONEE / Lydec / Amendis
Property title or ownership certificate of the land.
Complete architectural project (plans, sections, facades) signed by an accredited architect.
Topographical and site plan of the land.
Stability study (structural calculations) signed by an accredited engineer.
Copy of the National Identity Card (CIN) or passport of the applicant.