Ivory Coast
Administrative guide — Building permit
Verified on 29/04/2026
Average delay
120
days
Estimated cost
1,500,000 – 4,000,000 XOF
Office
Directorate of Construction and Urban Planning
CIE
SODECI
Property title (Certificate of Ownership, Definitive Concession Decree) or certificate of legal land possession.
Complete architectural plans (site plan, mass plan, floor plans, sections, elevations) signed by a certified architect.
Technical study (structural plans, foundations, framework) for complex constructions, signed by a certified engineer.
Tax clearance certificate issued by the municipality or district.
Duly completed building permit application form.