Beam-and-block floor slab in Algeria
Preview
Track material prices
Price ranges and 3-month trend, by country.
In short: A precast beam-and-hollow-block floor gives an economical slab with little formwork: the joists carry the hollow blocks, then a reinforced concrete topping ties everything together.

Local material prices in Algeria
Median of published surveys, in local currency with euro equivalent. “Indicative” prices come from the DiasporaBuild reference table and are updated as field surveys are added.
| Material | City | Median | Range | ≈ EUR |
|---|---|---|---|---|
| Rebarquintal 100 kgIndicative | Alger | 12 600 DZD | 12 600 DZD – 12 600 DZD | 83.69 € |
Price alert by email
Get an email if the median price of “Rebar · Algeria” moves by 5% or more (at most one email a week).
- • Typical thickness: 16 + 4 cm (span up to ≈ 4.5 m) and 20 + 5 cm (span up to ≈ 6 m)
- • Joist spacing: 60 cm (block width)
- • Topping slab: 4-5 cm with ø5 welded mesh at 15 × 15 cm
- • Intermediate props every 1.2-1.5 m for at least 7 days, strip progressively
- • Bearing: at least 10 cm on ring beam or load-bearing wall, and a perimeter ring beam is mandatory
- ✗ No props or props removed too early: deflection and cracks
- ✗ Mesh forgotten or badly positioned in the topping
- ✗ Joists with insufficient bearing on the walls
- ✗ Topping concrete poorly compacted or too wet
Frequently asked questions
How much do materials for beam-and-block floor slab cost in Algeria?
Rebar (Alger) : 12 600 DZD / quintal 100 kg (12 600 DZD – 12 600 DZD) — indicative.
What is the maximum span of a 16+4 beam-and-block floor?
About 4.5 m under ordinary residential loads. Beyond that, use 20+5 or a solid slab, after an engineer's advice.
Beam-and-block floor or solid slab?
Beam-and-block is lighter and needs less formwork; a solid slab is stronger for long spans, heavy loads or balconies.
What mistakes should I avoid with beam-and-block floor slab in Algeria?
No props or props removed too early: deflection and cracks. Mesh forgotten or badly positioned in the topping. Joists with insufficient bearing on the walls. Topping concrete poorly compacted or too wet.